Tender Schedule vs. Baseline, Recovery and Revised Schedule

A project may have several schedules as it moves from bidding to delivery. Here is how tender, baseline, recovery and revised programmes differ.

There are several different schedules a project may have as it moves through its various stages. One is prepared for the bidding process, another is approved once the contract is awarded, and others are required when the work falls behind or the original programme has to be changed following an approved change.

Tender Schedule

Prepared at the bidding stage, the tender schedule is generally not as detailed as what follows since it is based on the information, specifications, and drawings available at tender.

It will typically set out the key milestones and activities, major work sequences, basic resource assumptions, and the proposed duration through to the tender completion date. In essence, it is there to support the tender price and demonstrate to the client that the contractor can complete the work within the proposed time.

Baseline Schedule

Once the contract is awarded, the baseline schedule is the approved programme against which all schedule performance and progress are measured. It is a more detailed document that lays out activity relationships, the critical path, float, and any constraints or calendars being used.

Where necessary, it will also detail planned costs and resources, as well as key milestones and durations. During the project, this is what is used to check actual progress and forecast dates for variance.

Recovery Schedule

If the project is running behind the approved plan and the completion date is at risk, a recovery schedule is prepared. This programme is designed to show how lost time can be recovered and whether the target date is still achievable. To that end, it might call for fast-tracking or crashing of activities, a change in work methods or sequencing, or additional resources, hours, and shifts.

Revised Schedule

Approved changes to the existing programme require a revised schedule. Whether the reason is a variation, a design or scope change, an unforeseen event, or a contractual change, the revised programme will update the dates, activities, and relationships accordingly. If the project's change-control process requires it, the revised schedule can serve as the new baseline.

What Is the Difference?

ScheduleMain Purpose
TenderShows the proposed programme during bidding
BaselineThe approved programme for project control
RecoveryShows how delays can be reduced
RevisedUpdates the programme after approved changes

NEXT STEP

READY TO TAKE CONTROL OF YOUR PROJECT?

If your project needs stronger planning, more reliable schedule information, or better visibility of performance, DCD-GS can provide the specialist support required.

REQUEST A CONSULTATION

Share a little about your project. We will respond with the most relevant specialist.